Tuesday, May 15, 2018

Update

Spoke to our SS yesterday and now we have a comprehensive list of what is booked in for when - so we are hoping we can stick to this. The SS also mentioned that PCI will most likely be mid to late August.

Forecast:

Week 18: Cladding to be completed
Week 19: Electrical Wiring Rough in
Week 20: Gyprock
Week 21: Stairs

Then I am assuming we will hopefully be at lockup stage..

On the other hand, today I was going through furniture websites for 'fun' and I came across a great deal for a pair of sofas that I really liked! They offered to do 20% deposit for a forward order so they can order this when its time to move in to our brand new home!

Fingers crossed all goes well for us and we can be at lockup stage by mid June.

AND fingers crossed time will go by quickly so I wont have to think about it much longer.