Sunday, July 22, 2018

Week 26.1 - Bathrooms Completed & Other Bits

End of week 26 saw the below all being completed or started:


-          Wall tiles complete.
-          Benchtops in for the kitchen.
-          Painting started
-          Niches done with mosaics
-          Benchtops in bathroom complete
-          Sinks on in the bathroom
-          Kitchen sink went in
-          Painting started
-          Cupboard doors painted
-          Window architraves painted
-          Stairwell gypbrocked
-          Mosaic tiles in bathroom complete
-          Air vent cutouts done
-          Power point cutouts done

Also, more good news is that our SS called and said we may be able to have walk through in 4 weeks!

We are beyond excited at this point. Cannot believe this is actually happening and that we may be in our brand new home next month! 

Some photos below :) 

Shower Niche Mosaic Tiles

Vanity tops and sink

ensuite Shower

Ensuite Vanity

Air vent cutouts

Leisure Room Electrical Cutout

Kitchen Sink

Kitchen Benchtops

Powder Room

Laundry


Single Toilet Upstairs

Main Bath Upstairs Shower

Sunday, May 13, 2018

Week 15: Aircon & Electrical

This week they have started on the aircon ducts and electrical work. Supervisor promises that next week the lower roof will be going on and cladding will be done. Cannot wait for them to start on the inside and make it look like a proper home!
We are so far 14 Weeks from date of completion according to contract date. Sincerely hope that this does not push on past this as I just want to move in already. I didn't realise how impatient I was until we have started this build.