FINALLY after months and months of waiting and lengthy admin procedures, our customer service rep told us to expect our draft end panel and construction plans next week!
Basically, I am hoping that the slab will be poured before Christmas and my husband can start the party wall (he's a bricky) and complete before frame work goes on (probably next year).
You can imagine my excitement as we all know how bloody long it can take during the admin stages.
These are the dates I have so far which we have completed and forecast.
27.5.17
|
Contract
Signed
|
5.6.17
|
Balance of
5% Received
|
5.6.17
|
W Gallery
Appointments Booked
|
11.7.17
|
Landscaping
Plan Approved by you (required for BASIX lodgement)
|
12.7.17
|
BASIX
lodged
|
26.7.17
|
BASIX
Approved with Gas HWS Upgrade
|
1.8.17
|
BASIX
Re-lodged per Client Request to Pre-July Requirements
|
30.8.17
|
BASIX
Returned with Rejection due to Granny Flat
|
05.10.17
|
Lodgement
of Docs to Certifier for Final Approval
|
week of the 9th Oct (forecast)
|
Final
Approval
|
week of the 9th Oct (forecast)
|
CDC Vari
and Draft End Panel Issued to you for Signing
|
week of the 9th Oct (forecast)
|
Construction
Plans and Final Docs Prepared and Issued to you for Final Bank Approval
|
end of October (forecast)
|
File release (out of admin)
|
November (forecast)
|
Site Start
|
Basically, I am hoping that the slab will be poured before Christmas and my husband can start the party wall (he's a bricky) and complete before frame work goes on (probably next year).
If anyone is building we would love to hear your experiences!
Will keep this blog updated on how the build is going and will definitely upload some pictures!